Q: What is the current status of the intersection project at Boundary St. and North Park Way? Has it been officially completed, or are there ongoing efforts to address the issue?
A: Two issues that are preventing the traffic signals from going up at Boundary St and North Park Way are:
New luminaires – Â to meet current CT lighting requirements are expected to be delivered late-October. The signal light work at the Boundary and North Park Way is expected to be completed within 1-2 after receipt of the luminaires.
Safety clearance SW Corner – An existing low electrical line that conflicts with the per-plan new mast arm (arm where signal lights hang). A new modified mast arm is on-site but waiting for the luminaires that are tentatively scheduled to be delivered late October.